weekly news

  • 16 / 11 / 2020
  • -

Week:  16->20 November 2020

Here is the news of the week at SHAPE 2020:

·       Preparation of the foundations for the second phase of construction

 

We continue this week with the preparation of the foundations for the second phase of construction which will begin in mid-December.
 

·       Dismantling of garages at Ottawa


We are beginning the dismantling of garages G1 and G3 in Ottawa in preparation for their demolition.


·       Asbestos Removal in Ottawa 2

This week, following the completion of Mercury 2 asbestos removal on Tuesday, we will begin the removal of asbestos from Ottawa 2.

·        Continuation of the installation of the new sewers

We are cleaning up the surroundings of Rogers 3 this week. We will also soon begin the new rainwater network in the Rogers area.

·       End of the trench in the school and nursery area

Following the installation of the new coating last week, we are cleaning the area this week and removing the barriers early next week.