-
Gardening work – private surroundings
-
Demolition work in zone 600 Rogers 2 – 01/10 to 24/10
-
Demolition work in zone 600 Stone 6 - 13/09 to 08/10
-
Demolition work in zone 600 - Rogers 1 - 29.08 to 23.09
Presentation of the Project
The Shape’s homes are currently being rebuilt to provide residents with a quality of life that meets their needs.
600 homes will be rebuilt in 3 phases, over a period of 6 years. Demolition work, development of road networks, drainage infrastructure and construction of the new buildings will therefore be implemented in areas 600 and 800.
The works have started in August 2020 and will end in December 2026, to finally offer 300 houses and 300 flats, with an excellent standard of living for the inhabitants.
The purpose of this website is to inform you about the different phases of the construction work and its progress throughout the project.
Housing construction in area 600
The first phase of the project will run from June 2020 to April 2022 and will focus only on the 600 area.
This same phase is subdivided into 4 sub-phases in order to distribute the demolition and construction stages. This is to ensure both good traffic in the area for residents and to maintain a certain number of dwellings.
1. Phase 1.1
Duration: from 04/06/2020 to 29/04/2021
During this period, construction work will be carried out on the current soccer field (blue area in the pictures). In parallel, demolition work in the green zone on the images will take place in order to prepare the construction phase of the new housing in phase 1.2.
2. Phase 1.2
Duration: from 09/10/2020 to 09/09/2021
Construction of the new housing will take place in the green zone, not far from the current soccer field. In parallel, the demolition of the yellow zone will take place to prepare for the next phase of construction.
3. Phase 1.3
Duration: from 03/02/2021 to 17/01/2022
Construction will take place in the yellow zone. The demolition work will be carried out in the pink zone in order to prepare the last phase of construction of housing in the 600 area.
4. Phase 1.4
Duration: from 19/05/2021 to 15/04/2022
The very last dwellings in zone 600 will be built at this time in the pink zone.
Construction of housing in the first part of zone 800
The second phase of the project will run from May 05, 2022 to April 08, 2023 and will focus on the first part of the 800 area.
As for the first phase of the project, phase 2 was divided into 4 sub-phases to guarantee traffic flow for residents and a sufficient number of dwellings throughout the project
1. Phase 2.1
Duration : from 05/05/2022 to 08/04/2023
The construction work will start in the area 2.1 (yellow on the image). A few months later, the demolition of the area 2.2 (pink area on the image) will start to prepare for the next phase of construction.
2. Phase 2.2
Duration : from 22/09/2022 to 31/08/2023
The construction of housing units in the area 2.2 (pink on the image) will start. Demolitions in area 2.3 (in green in the picture) will also begin some time later in preparation for the construction of phase 2.3 housing.
3. Phase 2.3
Duration : from 19/01/2023 to 18/12/2023
The construction of housing units in the area 2.3 (green on the image) will start. Some time later, the demolition for the last phase (2.4) will start.
4. Phase 2.4
Duration : from 05/05/2023 to 08/04/2024
End of construction work in this part of area 800. The last homes will be built in the blue area on the image.
Last constructions in the areas 600 and 800
The third and final phase of the Shape Village reconstruction project will take place in areas 600 and 800.
In the 600 area :
Trees will be planted, a few last dwellings and small road elements will be built.
1. Phase 3.1 (area 600)
Duration: from 04/30/2024 to 03/04/2025
The last developments are being carried out in area 600, including the last sections of roads and car parks.
2. Phase 3.2 (area 600)
Duration: 18/09/2024 to 19/08/2025
We make the surroundings: we lay out the gardens, plant new trees and build a new building.
3. Phase 3.3 (area 600)
Duration: from 10/01/2025 to 28/11/2025
A few final dwellings will be built.
In the 800 area :
This last phase will mainly focus on the construction of new housing in the northern part of the 800 area, but will also include the latest road works and improvements to the surroundings.
1. Phase 3.1 (area 800)
Duration: 08/05/2024 to 03/04/2025
In the area of housing already built, the last road works and the construction of parking spaces will be carried out.
A whole new housing area will also be built (yellow area on the image). In parallel, some time later, the green zone will be demolished to prepare the space for construction.
2. Phase 3.2 (area 800)
Duration: 18/09/2024 to 19/08/2025
Construction of phase 3.2 housing (green area in the image)
In January, housing in zone 3.3 (pink on the image) will be demolished.
The planting of trees and landscaping of the gardens will also be carried out during this period for the 800 area.
3. Phase 3.3
Duration: 10/01/2025 to 28/11/2025
Construction of the last housing units in area 800 (pink zone in the image)