Here is the news of the week at SHAPE 2020:

Demolition of garages at Stone


Following the demolition of Stone 4, this week we will demolish the garage batteries G12, G14, and G15.
 

·       Beginning of interior dismantling in Ottawa 2


We will begin dismantling the interior of the Ottawa 2 building. The objective is to sort the materials prior to demolition.


·       End of asbestos removal at Mercury 2

This week, we are completing the asbestos removal in the Mercury 2 apartment block.

·       Continuation of the installation of the new sewers in the Rogers Area

We are completing the installation of the new sewers behind Rogers 1. At the same time, we continue to lay new sewers next to Rogers 3.

At the end of the week, we will start laying the sewers in the area in front of Rogers 2.

·       End of the trench in the school and nursery area

This week we are closing the trench and repairing the different parking lots and roads.

For more information: contact us at 0490 58 93 38, at the following email address: shape.village@bpcwallonie.be, or on https://shape-village.com/en/.