As part of the reconstruction of the SHAPE-Village, we will demolish the Rogers 3 building. This demolition work is scheduled to start on 05/08 and will last 18 working days.

In order to limit dust as much as possible, various protective measures will be put in place: watering, misters, tarpaulin fences, (as long as this measure is compatible with the weather)...

To ensure the necessary watering during the demolition, traffic on Venus Street will have to be interrupted (see traffic plan below). The houses located on this street will remain accesssible by car.

Despite the protective measures provided, we unfortunately can not guarantee that all dust will be contained in the demolition area. During working hours (7:00 a.m. to 5:30 p.m); we advise you not to put loundry to dry outsite, not leave your windows open and to bring in your garden furniture.

The working hours (7:00 a.m. to 5:30 p.m.) will be scupulously respected so as not to cause noise pollution outside this time slot.

We apologize for the disturbing, and we thank you in advance for your cooperation, which is essential for the smooth progress of the work.