Trenches
- 28 / 02 / 2020
Preliminary work for the reconstruction of the SHAPE Village continues. The second phase consists in digging trenches in 13 sections in the 600 area to place cables and pipes (water, electricity, gas, VOO, Proximus and street lighting).
Prior to the realisation of each trench, we will carry out ground surveys.
Like for trench 1, a notice will be sent to you in due time with schematics showing the exact location of the surveys. They will also be marked on site.
The current planning for the surveys and the trenches is as follows:
This timeline will change according to weather conditions, worksite events, and unforeseen events due to discoveries in the ground. It will be regularly updated on our website at https://shape-village.com/en/ . So don’t hesitate to check it out regularely!
The trenches have been marked on site and we will also label the various storage site locations.
We will do our utmost to reduce any inconveniences linked to our work (placement of steel slabs if needed to access a garage, pedestrian footbridges, ...).
For safety reasons, we ask you not to walk near the work areas or enter the storage areas, to respect the markings (orange nets, rubble, Heras barriers, etc.) and to cross the trenches only at the footbridges provided for this purpose.
Thank you in advance for your collaboration.
Do you have any questions?
Need more information : contact us on 065/72.37.31