Pipeline strengthening work
- 14 / 02 / 2020
As you probably know, the SHAPE2020 group was designated to carry out the reconstruction work on the Shape Village. The start of this work is fast approaching.
In this context, the SHAPE2020 group will carry out preliminary work. The first phase of this work consists in strengthening the pipeline in preparation of the future road that will cross over it.
This work is essential for the realization of future developments.
This work will be carried out according to the schedule below and in the area indicated on the provided schematic. Please note that these dates may change depending on weather conditions.
- 17/02 : Arrival of the digger and start of the excavation ;
- 18/02 : Excavation and delivery of the protective shell ;
- 19/02 : Strength test and localized repairs if needed ;
- 20/02 : Installation of the protective shell ;
- 21/02 : Closing of the hole, and transfer of extra soil to storage.
It is important to note that the work areas will be marked up with barricade tape. For your safety, we ask you not to enter these marked areas from 17/02 until the end of the work and the removal of the marking.
Thank you in advance for your collaboration.